Have a say. Write to Empire State Development about Atlantic Yards. Written comments on the scope of the environmental review closed at 5 PM on October 26. The next formal comment period, on the Draft Environmental Impact Statement and the amended plan, comes in 2027, and the state holds a workshop on the proposed open spaces in November.
Search an address or a corner to see whether it is inside the project, which community board it is in, and the nearest building planned for Phase II. Tap any building or site for its description, zoning and land use.
A state project, not a city one. Empire State Development, the state’s economic development agency, approved it in 2006, and its plan overrides city zoning, so it never went through the city’s land use process.
As approved, Atlantic Yards is a 22-acre, $4.9 billion project: the 18,000-seat Barclays Center, a rebuilt Long Island Rail Road yard and subway upgrades, 16 residential and commercial buildings with up to 6,430 apartments, 2,250 of them affordable, and eight acres of publicly accessible open space. The site is bounded by Atlantic Avenue to the north, Dean Street to the south, Vanderbilt Avenue to the east, and Flatbush Avenue and 4th Avenue to the west, in Prospect Heights.
Phase I is the part on solid ground between Flatbush Avenue and Vanderbilt Avenue south of the railyard: the arena, eight apartment buildings, three acres of open space run by the Pacific Park Conservancy, an updated subway entrance, an upgraded LIRR yard, a public middle school and a health care facility. Phase II is everything left: the two railyard blocks between 6th Avenue and Vanderbilt Avenue, which need a deck built over working tracks before anything can go on them, Site 5 across Flatbush Avenue at 4th Avenue, and B1, the arena plaza.
The footprint straddles Community Boards 2, 6 and 8. Two of the eight buildings, 461 Dean Street and 38 Sixth Avenue, sit in BKCB6. The arena, 18 Sixth Avenue, the railyard and Site 5 are in BKCB2. Pacific Park, 662 Pacific Street, 550 Vanderbilt Avenue, 535 Carlton Avenue and 595 and 615 Dean Street are in BKCB8.
Where it sits: three boards, one project
The project’s 21.7 acres of tax lots, split by community board, and what is on each part. The boards do not overlap each other; the project overlaps all three. Built apartments are outlined in orange.
The land, by board
61.6%
13.7%
24.7%
BKCB2, 13.4 acresBKCB6, 3.0 acresBKCB8, 5.4 acres
What is on each board’s part
Bars to scale, in acres.
Built apartmentsBarclays CenterOpen space lotsUnbuilt, Phase II
BKCB2
Built 0.6, arena 3.7, unbuilt 9.1 acres: 18 Sixth Avenue, 62.5% of the arena lot, Site 5, B1 and the whole railyard
BKCB6
Built 0.8, arena 2.2 acres: 461 Dean Street, 38 Sixth Avenue and 37.5% of the arena lot. Nothing unbuilt
BKCB8
Built 3.7, open space 1.7 acres: 662 Pacific Street, 550 Vanderbilt Avenue, 535 Carlton Avenue, 595 and 615 Dean Street, and the open space lots. Nothing unbuilt
The apartments built, by board
3,210 apartments in the eight towers, 1,374 of them affordable.
All
858
666
1,686
BKCB2 26.7%, BKCB6 20.7%, BKCB8 52.5%
Affordable
258
484
632
BKCB2 18.8%, BKCB6 35.2%, BKCB8 46.0%. 73% of the apartments built in BKCB6 are affordable
Every building built
Eight towers on seven tax lots, all completed between 2015 and 2024. Tap a row to find it on the map. The orange edge marks the two in BKCB6.
Building
Parcel
Board
Apartments
Affordable
Share
Floors
Completed
The 876: the affordable housing still owed
The 2,250 affordable apartments were promised in 2005, and a 2014 settlement with the state set May 2025 as the deadline to finish them, with damages of $2,000 a month for every one not built.
Who the built affordable apartments are for has also been a fight. Most of the 1,374 are for middle-income households: of the 1,303 counted in the city’s housing data, 971 are for middle-income households, including every income-restricted apartment at 18 Sixth Avenue, 662 Pacific Street and 595 Dean Street. Phase II lowers the ceiling for income-restricted apartments from 165% to 120% of area median income.
Phase II: the plan for the rest
A new development team, Cirrus Real Estate Partners and LCOR, took over the unbuilt sites in October 2025 and signed a memorandum of understanding with the state on July 28, 2026. It is not binding; the state has to finish an environmental review and amend the project plan first.
Phase II as proposed, July 28, 2026
Up to 5,600 new apartments in seven towers, 1,242 of them income-restricted, 27% of the new rentals, at 40% to 120% of area median income, and at least 30% with two or more bedrooms. That brings the project to 8,812 apartments, 2,382 more than approved, and 2,616 income-restricted, 366 more than the 2,250 promised. Heights go up on every site: 799 and 570 feet at Site 5, 684 feet at B7, against 250 feet at Site 5 and 460 feet at B7 in the approved plan. B8 becomes open space instead of a tower.
What is in it
Build on solid ground first. Site 5 and B6, which sits partly on land below Atlantic Avenue, go first because neither waits on a deck over the tracks.
Affordability by building. 25% of rentals at an average of 60% of area median income at Site 5 and B6; 27.5% at an average of 80% at B5 and B10; 30% at an average of 90% at B7 and B9, with no income-restricted rent above 120%. All income-restricted apartments are permanent. 400 condominiums at Site 5, 300 at B7 and 300 at B9 have none.
Community space. At least 20,000 square feet, including an intergenerational community center in B6 and more space in B5 and B10, plus up to about 140,000 square feet of retail and an optional hotel at Site 5.
Public money and taxes. The first railyard deck depends on $350 million from the state, $175 million of it appropriated so far. The rental buildings can get a full property tax exemption for 40 years through payments in lieu of taxes, and Phase II is exempt from sales taxes and from mortgage recording taxes on construction loans.
Deadlines. The first deck, Block 1120, done by the end of 2032; Site 5 and the Block 1120 buildings by the end of 2037; Block 1121 by the end of 2040 with a funding agreement and 2042 without one. Each extension costs $500,000 the first year and $1 million the second, paid toward affordable housing.
Where the review stands
The state released its Draft Scope of Work for a Draft Second Supplemental Environmental Impact Statement on August 24, 2026, and held a public scoping meeting on Zoom on September 24. Written comments on the scope closed at 5 PM on October 26, 2026. Next, in 2027: the Draft Environmental Impact Statement and the Amended Modified General Project Plan, a public hearing and comment period, then a vote of the Empire State Development board.
Every Phase II building, as proposed7 sites
Site
Height
Rentals
Income-restricted
Average, % of area median income
Condos
Total
Who decides
Empire State Development makes the decisions. The Atlantic Yards Community Development Corporation, created in 2014, reviews changes to the plan and construction impacts and advises the state’s board.
The AY CDC has 14 directors: nine appointed by the Governor and one each by the State Senate’s President Pro Tem, the Assembly Speaker, the Mayor, the Council Speaker and the Brooklyn Borough President. Phone (212) 803-3736.
Shawn V. Austin Seth Bynum Trenelle Gabay Drew Gabriel Marc Jahr Mitch Korbey Daniel M. Kummer, Chair Sayar Lonial Tamara McCaw Ronald Shiffman Ethel Tyus Gib Veconi Deborah Young
CB6 and Atlantic Yards
From the board’s own minutes.
Jan 13, 2010
The district manager reports streets closing for good on February 1: 5th Avenue between Flatbush and Atlantic, Pacific Street between 5th and 6th Avenues, and Pacific Street between Vanderbilt and Carlton Avenues. 6th Avenue between Flatbush and Pacific, and Carlton Avenue between Dean and Pacific, become two-way.
CB2, CB6 and CB8 agree to seek a commitment that all three boards keep qualifying for the project’s hiring and affordable housing preferences wherever the lines are drawn.
Sep 15, 2015
The Executive Committee backs CB8’s position that the project’s new school be a middle school, sited to keep students away from dangerous traffic.
PlanThe state approves the project. A federal eminent domain suit was filed that October.
Jun 23, 2008
CourtsThe U.S. Supreme Court declines the eminent domain appeal; New York’s highest court dismisses the last state challenge in November 2009.
Sep 2009
PlanThe state approves a renegotiated plan; the cap on affordable rents rises to 165% of area median income.
Feb 1, 2010
CB6Three street segments close for good, including 5th Avenue between Flatbush and Atlantic.
Mar 11, 2010
ArenaGroundbreaking for the arena.
Sep 21, 2012
ArenaBarclays Center opens.
Dec 18, 2012
HousingGround broken for B2, the first apartment building, at 461 Dean Street.
Jun 2014
HousingThe state settles with the developer: all 2,250 affordable apartments by May 2025. The AY CDC is established, and that summer Greenland takes a 70% stake.
HousingThe affordable housing deadline passes with 876 apartments unbuilt.
Oct 2025
PlanCirrus Real Estate Partners and LCOR win the railyard sites at the foreclosure auction; the state approves them on October 7 and takes $12 million in place of the damages.
Nov 2025 to Mar 19, 2026
PlanFour public workshops and an online survey on the unbuilt sites; the state publishes a Community Engagement Report.